IRAQ - WQ-2 GTPP  -  Supervision, integration and commissioning of CCTV and ACS

Gas Turbine Power Plant (GTPP) 
West Qurna-2, Basrah, Iraq 
ENKA Insaat (https://www.enka.com/) - Lukoil Mid-East Limited (https://mideast.lukoil.com/en)
 Participation in project: 03.2014 - 06.2014


ENKA Insaat (Turkey) has been contracted for construction of a gas turbine power plant witch supply power to all oil production facilities on Mishrif field. 
As ENKA contractor for this project, we constructed the professional IP video surveillance system and access control system with automated vehicle barriers and full height turnstiles, performed installation supervision, commissioning and integration between CCTV and ACS

 


Equipment used: 

 IP video surveillance system - Bosch, NetApp 

Access control system - Bosch 

Full height turnstiles - KABA

Automated vehicle barriers - KABA 

Network equipment - CISCO, NSGate, MOXA 

 Uninterruptible Power Supply - APC